We have done a fundamental analysis of Sanima Middle Tamor Hydropower Ltd (TAMOR).
Sanima Middle Tamor Hydropower Ltd (TAMOR)
Following is the company analysis of Sanima Middle Tamor Hydropower (TAMOR).
Introduction
Sanima Middle Tamor Hydropower Limited is a hydropower company that was established in 2016. The corporate office of the company is located ainDhumbarahi, Kathmandu Nepal. Similarly, Its project name is called Middle Tamor Hydropower Yojana which has a 73MW electricity-producing capacity. The project of the company is located in the Taplejung district of Nepal.
The project is constructed under the BOOT (Build, Own, Operate, and Transfer) mechanism.
More Information
Particulars | Information |
---|---|
Name | Sanima Middle Tamor Hydropower Limited. |
Symbol | TAMOR |
Sector | Hydropower |
Listed Share | 33,325,000.00 units |
Face Value | Rs. 100.00 |
Paid Up capital | Rs. 3,332,500,000.00 |
Address | Dhumbarahi, Kathmandu Nepal. |
sanima@sanimahydro.com | |
Phone Number | +977-1-4372828/4373030/4015788. |
Audited Financial Statement
Following is the detail information of audited financial statement
Particulars “000” | FY 2077/78 | FY 2078/79 |
---|---|---|
Paid up capital | 2,332,750.00 | 2,499,375.0 |
Reserve and surplus | 15,217.00 | (39,189.00) |
Debt | – | – |
Revenue | – | – |
Net Profit | (30,066.00) | (56,597.00) |
Earning Per Share | (1.29) | (2.26) |
Net Worth Per Share | 100.65 | 98.43 |
Return on Equity | (0.13) | (0.23) |
Information About Project
Following is the detailed information of the company
Particulars | Information |
---|---|
Name of the Project | Sanima Middle Tamor Hydropower |
Types of Project | Run of River |
Installed Capacity | 73 MW |
Electricity generation Licensed Received | 29th Jestha, 2074 |
Generation Valid Date | 21 Jestha, 2110 |
RCOD | 26th Bhadra, 2080 |
Total Cost | Rs. 13.33 arba |
Cost per Megawatt | Rs. 18.26 crore |
Shareholding Structure
Following is the shareholding structure
Particulars | Percentage |
---|---|
Promoters Shareholders | 70% |
General Holdings | 30% |
Capital Structure
Following is the Capital Structure of the company
Particulars | Amount |
---|---|
Authorized Capital | 3,500,000,000.00 |
Issued Capital ( After IPO) | 3,332,500,000.00 |
Promoters | 2,332,750,000 |
General Public | 999,750,000 |
Board of Directors
Following is the boards of directors
Name | Position |
---|---|
Mr. Binaya K. Shrestha | Chairman |
Ms. Usha Khatiwada | Director |
Er. Braj Bhusan Chaudhary | Independent Director |
Mr. Apar Neupane | Director |
Er. Shiv Kumar Basnet | Director |
Hence, these are the company analysis of Sanima Middle Tamor Hydropower (TAMOR).
Frequently Asked Question
IPO results day of Sanima Middle Tamor Hydropower.
= IPO result will be published after a few weeks of IPO application.
Head Office of Sanima Middle Tamor Hydropower?
= Head Office of Sanima Middle Tamor Hydropower is located at Shankha Park, Dhumbarahi, Kathmandu Nepal.
Phone Number of Sanima Middle Tamor Hydropower?
= +977-1-4372828/4373030/4015788 is the phone number of Sanima Middle Tamor Hydropower.
What is the hydropower capacity of Sanima Middle Tamor Hydropower?
= 73 MW is the hydropower capacity of Sanima Middle Tamor Hydropower.